A budget overrun announces itself weeks in advance. If you see the signals, you can still decide. If you only find it at month-end, all you can do is explain.
Why the overrun is so often noticed too late
The figures usually exist, but in three places and too late: the budget is in the quote, the plan in a spreadsheet, and the hours arrive in bulk at the end of the month. By the time someone puts it all side by side, the money is spent.
There is also a flaw in the thinking: the classic target/actual comparison looks back. It tells you how much budget has been used, but not whether the remaining work fits. That is exactly the question that decides whether the project succeeds.
Five signals of a looming budget overrun
The plan is above the budget. The scheduled hours and costs alone exceed the project budget.
The forecast runs beyond the budget. Actuals to date plus the plan for the coming months add up to more than the target.
A single pot is overdrawn. One activity or cost type uses more than intended while the project as a whole still looks unremarkable.
Spending is ahead of progress. 70 per cent of the budget is booked, but only half of the milestones have been reached.
Dates are slipping. Overdue milestones almost always mean additional effort.
The method: target, plan, actual and forecast
Early detection needs three figures per project and per budget pot that always stand side by side:
Target is the budget: the project budget and its split into pots.
Plan is the hours and costs the team schedules month by month.
Actual is the booked time, valued at the day rate, and the booked project costs.
Actuals and the plan for the coming months give the forecast to project end. If the plan or the forecast is above the target, action is needed, even when actuals are still far below the budget.
Try it
The need to act catches your eye
Three projects, three states. Without reading a single number you see which project needs your attention.
Target: the budgetPlan: the planned time and costsActual: the booked time and costs
Try it yourself:
Website-RelaunchNordlicht GmbH
On track
Target
120,000 €
Plan
112,400 €
Actual
68,250 €
Plan and actual are within budget, 7,600 € in reserve.
Project progress 58%
ERP rolloutKessler Maschinenbau
Watch
Target
80,000 €
Plan
92,000 €
Actual
41,200 €
The plan is 12,000 € over budget.
Project progress 50%
App-EntwicklungStadtwerke Süd
Action needed
Target
60,000 €
Plan
58,000 €
Actual
68,400 €
The budget is already exceeded by 8,400 €.
Project progress 85%
1 of 3 projects needs your attention, and you can see it without reading a single number.
The dashed line is the budget limit. Anything beyond it turns yellow (planned) or red (booked). The same traffic light appears in the application on every project and every budget pot.
Spotted early means more room to act
The value of early detection lies in the decisions it still makes possible. As long as budget remains, you have options:
Prioritise scope. Agree with the client what is essential and what can be dropped or come later.
Negotiate a change order. Raise additional effort while it is still ahead, not after it has been incurred.
Replan the team. Redistribute tasks or bring in capacity from another project.
Reallocate budget. Move reserve from a pot that is on plan to the overdrawn one.
Once the budget is already exceeded, usually all that remains is to justify the deviation.
How 99BRICKS supports early detection
Early warning
How you see the need to act weeks earlier
A warning at the planning stageThe traffic light turns yellow as soon as planned hours and costs exceed the budget. That is before the first of those hours is booked.
Forecast at project endActuals to date plus the plan for the coming months give the forecast. You see where the project will end up if nothing changes.
Every budget pot on its ownBudgets are monitored per activity and cost type. An overdrawn pot stands out even when the project as a whole still looks fine.
Weekly report from the project leadBudget, schedule and quality as traffic lights, with reasons and measures. Controlling sees the system figures and the assessment side by side.
Frequently asked questions
How do I detect a project budget overrun early?
By not only comparing actuals with the budget but also including the work still planned. 99BRICKS adds actuals to date and the plan for the coming months into a forecast and flags it as soon as it exceeds the budget.
What is the difference between target, plan and actual?
The target is the budget of the project and its pots. The plan is the hours and costs the team schedules month by month. The actual is the booked time, valued at the day rate, and the booked project costs.
Why is a target/actual comparison not enough?
It only shows an overrun once it has happened. If the plan is above the budget or the forecast runs beyond it, the need to act is visible weeks earlier. Then you can still replan, prioritise or renegotiate.
How current are the figures in project controlling?
Every booked hour and every booked invoice immediately affects actuals, forecast and traffic light. Because the team books its time daily on project and activity, you do not have to wait for month-end closing.
Who is 99BRICKS for?
For companies that run projects with a budget: agencies, consultancies, IT service providers, engineering and planning offices, and internal project organizations. It pays off from the first project in which several people book time against a budget.
Do I need a separate time tracking tool?
No. Time tracking is part of 99BRICKS. Employees book their working time directly on their assigned activities; actual costs, forecast and timesheet follow from that with no further steps.